San Francisco Oakland Bay Bridge Demolition

PROJECT     The East Span of the San Francisco Oakland Bay Bridge had been replaced, leaving a line of concrete piers nearly 2 miles long in one of the world’s busiest harbors.   Removing them was the final stage in the 4-year, high profile bridge seismic safety replacement project. 


SOLUTION      The initial attempt to demolish the piers by hammering was rejected due to the detrimental effects on water quality and the bay fishery.   Hammering is messy; air quality monitors don’t like it due to dust and noise, effluents are hard to contain therefore water quality regulators don’t like it, and fish biologists don’t like it for all those reasons.  It was determined that cutting the “pillar” portion of the piers above water into blocks sized for removal would be a cleaner and more efficient method.     

Kiewit/Manson AJV was operating within a 4-month window to remove the above-water portion of the piers, each weighing approximately 320 tons, before the seasonal migration when most fish departed the harbor and the remaining underwater portion could be exploded.   Bluegrass mobilized men and equipment to Oakland.  

CHALLENGES   The job required skill and efficiency, but was not particularly complex.   Slurry control was critical, and we are experienced meeting such requirements.  Our men and equipment operated steadily, cutting pier after pier into 4 blocks weighing approximately 80 tons each.  The first 4 piers were completed in half the anticipated time, and the contract was extended to cut and core drill 4 more.  Those 4 were cut and drilled for rigging, and the contract was extended again.  In all we wire sawed 10 piers and core drilled 9.   

OUTCOME   With men and equipment operating at peak performance, we finished cutting the last of 10 piers in the time initially allocated for cutting 4, advancing the removal project a year ahead of schedule.   We accomplished this with a perfect safety record and no environmental violations.   Bluegrass was awarded Best Partner by Kiewit/Manson AJV.  Nominated by Caltrans, Bluegrass was the first subcontractor to receive this quarterly award.   

Your early success was instrumental in allowing our project the opportunity to complete, two seasons worth of inwater work in one season, affording us, Kiewit Manson AJV, the ability to beat our CPM schedule by a full year.      -- Zach Reilly, Project Manager   Kiewit / Manson AJV

 
  

 

 

 

<< Back

Contact Us

Our experts are available to provide a quote or discuss your project. We have delivered creative concrete and metal cutting solutions since 1979, and welcome the opportunity to assist you.

Request A Quote

Safety

The Bluegrass culture promotes a safety first attitude. On job sites our technicians are prepared, aware, equipped and committed to safe practices.

Read More

Resources

We mobilize a full spectrum of resources to deliver prompt, successful results: highly trained personnel, dependable equipment, diamond wire saws, robotic hammers, a machine shop and more.

Learn More

FAQ

If your question is not answered here, contact us to discuss your project. Our experienced staff is prepared to provide solutions to any metal and concrete demolition challenge.

Learn More